Telehouse Phase 1

Data Centre

Project Details

Multi story enterprise data centre in a very restricted site in Canary Warf. Holden designed, supplied and delivered a complex arrangement of mesh, fire rated wall, doors, and structural grid ceiling. The key challenge on this project was designing solutions for complicated interfaces that could be installed in the required sequence for our client.

Date:2018
Value:€0.9 million
Location:London
Client/Main ContractorMercury Engineering /Telehouse
Sector: Data Centre / Food / PharmaData Centre
Size: 
Duration: Approximately9 months